PNM-IA-PNM-2022-01
600 MW generation in San Juan, NM · In queue since January 2022 · Proposed COD August 2028
600 MW
Capacity
1
Components
Hydro
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
A proposed 600 MW hydroelectric generation project, identified as PNM-IA-PNM-2022-01, is under development in San Juan County, New Mexico. The project is listed in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of January 27, 2022. The proposed commercial operation date is August 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the San Juan 345 kV Switching Station.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
San Juan 345 kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-01