PNM-IA-PNM-2022-02
220 MW generation in Santa Fe, NM · In queue since April 2022 · Proposed COD June 2024
220 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed project PNM-IA-PNM-2022-02 is a 220 MW solar generation project located in Santa Fe County, New Mexico. The developer is PNM (Public Service Company of New Mexico). It consists of 220 MW of solar photovoltaic generation.
The project is currently active in the Public Service Company of New Mexico interconnection queue, with an entry date of April 7, 2022. It has a proposed commercial operation date of June 1, 2024, and its interconnection status is currently in the System Impact Study phase. The point of interconnection is the 345 kV Diamond Tail.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
345 kV Diamond Tail
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-02