PNM-IA-PNM-2022-03
100 MW generation in Santa Fe, NM · In queue since April 2022 · Proposed COD March 2025
100 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 11m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The proposed project, identified as PNM-IA-PNM-2022-03, is a 100 MW solar generation project located in Santa Fe County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area and has an interconnection point on the 115 KV Line from Britton to Algodones.
The project entered the PNM interconnection queue on April 4, 2022, with a proposed commercial operation date of March 1, 2025. Its interconnection status is currently in the System Impact Study phase. The project has appeared in recent news coverage regarding renewable energy development in New Mexico.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
115 KV Line Britton-to-Algodones
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-03