PNM-IA-PNM-2022-05
199 MW hybrid in Mckinley, NM · In queue since April 2022 · Proposed COD December 2025
199 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PNM-IA-PNM-2022-05 is a proposed 199 MW hybrid solar and battery project in McKinley County, New Mexico. The project, located in the Western region, consists of 199 MW of solar capacity. It is being developed within the Public Service Company of New Mexico (PNM) interconnection queue, under the queue ID PNM-IA-PNM-2022-05.
The project entered the queue on April 7, 2022, with a proposed commercial operation date of December 1, 2025. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Bluewater-Taylor 115kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Bluewater-Taylor 115kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-05