PNM-IA-PNM-2022-07
49.9 MW generation in Grant, NM · In queue since April 2022 · Proposed COD June 2024
49.9 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed project, identified as PNM-IA-PNM-2022-07, is a 49.9 MW solar generation project located in Grant County, New Mexico. The project is in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of April 8, 2022. Its proposed commercial operation date is June 1, 2024. The point of interconnection is the Luna 115kV Line.
The project's interconnection status is currently in the System Impact Study phase. The developer is PNM. Recent news coverage indicates public interest in renewable energy projects in New Mexico.
Generated from interconnection queue and public data sources
State
NM
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Luna 115kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-07