PNM-IA-PNM-2022-09
375 MW hybrid in Mckinley, NM · In queue since April 2022 · Proposed COD March 2025
375 MW
Capacity
2
Components
Solar + Battery
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 11m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The proposed project PNM-IA-PNM-2022-09 is a 375 MW hybrid solar and battery energy storage development in McKinley County, New Mexico. The project, located in the Western region, consists of a 250 MW solar array coupled with a 125 MW battery energy storage system. It is being developed within the Public Service Company of New Mexico (PNM) interconnection queue, under the queue ID PNM-IA-PNM-2022-09.
The project entered the interconnection queue on April 6, 2022, and has a proposed commercial operation date of March 1, 2025. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Yah-Ta-Hey 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Yah-Ta-Hey 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.