PNM-IA-PNM-2022-11
100 MW storage in Bernalillo, NM · In queue since April 2022 · Proposed COD January 2024
100 MW
Capacity
1
Components
Battery
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-01
PNM-IA-PNM-2022-11 is a proposed 100 MW battery storage project located in Bernalillo County, New Mexico. The project, under development by Public Service Company of New Mexico (PNM), consists of a 100 MW battery energy storage system. It is currently in the Public Service Company of New Mexico interconnection queue with an entry date of April 8, 2022.
The proposed commercial operation date for the project is January 1, 2024. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Reeves Generating Station.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Reeves Generating Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2022-11