PNM-IA-PNM-2023-01
250 MW generation in Cibola, NM · In queue since October 2022 · Proposed COD December 2025
250 MW
Capacity
1
Components
Wind
3y 7m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
The proposed project PNM-IA-PNM-2023-01 is a 250 MW wind generation project located in Cibola County, New Mexico. The developer is Public Service Company of New Mexico (PNM).
The project is in the Public Service Company of New Mexico interconnection queue, with an entry date of October 21, 2022. The proposed commercial operation date is December 1, 2025. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Ambrosia Lake - West Mesa 230 kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Cibola
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Ambrosia Lake - West Mesa 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.