PNM-IA-PNM-2023-02
200 MW storage in Sandoval, NM · In queue since January 2023 · Proposed COD March 2027
200 MW
Capacity
1
Components
Battery
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
PNM-IA-PNM-2023-02 is a proposed 200 MW battery storage project located in Sandoval County, New Mexico. The project, being developed by PNM, consists of 200 MW of battery capacity. It is interconnected to the Public Service Company of New Mexico (PNM) via the Cabezon 345 kV Substation.
The project is currently active in the PNM interconnection queue, having entered on January 3, 2023, with a proposed commercial operation date of March 1, 2027. Its interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
NM
County
Sandoval
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Cabezon 345 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.