PNM-IA-PNM-2023-03
200 MW storage in Bernalillo, NM · In queue since December 2023 · Proposed COD March 2027
200 MW
Capacity
1
Components
Battery
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
The proposed energy storage project PNM-IA-PNM-2023-03 is a 200 MW battery development in Bernalillo County, New Mexico. The project is located in the Western region and is being proposed within the Public Service Company of New Mexico (PNM) interconnection queue. The queue entry date is December 30, 2023, with a proposed commercial operation date of March 1, 2027.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Prosperity 115 kV Switching Station. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Prosperity 115 kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.