PNM-IA-PNM-2023-05
200 MW hybrid in Bernalillo, NM · In queue since January 2023 · Proposed COD March 2027
200 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
PNM-IA-PNM-2023-05 is a proposed 200 MW hybrid solar and battery project located in Bernalillo County, New Mexico. The development project, which consists of 200 MW of solar power, is in the Public Service Company of New Mexico (PNM) interconnection queue, under the queue ID PNM-IA-PNM-2023-05. The project's queue entry date is January 3, 2023, with a proposed commercial operation date of March 1, 2027. Its interconnection status is currently in the System Impact Study phase.
The point of interconnection for the project is the Ambrosia Lake / West Mesa 230 kV Line. The project is being developed within the Public Service Company of New Mexico (PNM) service area.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Ambrosia Lake _x0013_ West Mesa 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.