PNM-IA-PNM-2023-06
199 MW hybrid in Mckinley, NM · In queue since December 2022 · Proposed COD December 2025
199 MW
Capacity
1
Components
Solar
3y 5m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
3 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
The proposed project PNM-IA-PNM-2023-06 is a 199 MW hybrid solar and battery energy storage development in McKinley County, New Mexico. The project, located in the western region of the US, is being proposed within the Public Service Company of New Mexico (PNM) interconnection queue. The queue entry date is December 30, 2022, with a proposed commercial operation date of December 1, 2025.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Ambrosia 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Ambrosia 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2023-06