PNM-IA-PNM-2023-07
300 MW generation in Santa Fe, NM · In queue since January 2023 · Proposed COD November 2025
300 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
PNM-IA-PNM-2023-07 is a proposed solar generation project with a total capacity of 300 MW. The project is located in Santa Fe County, New Mexico, within the Public Service Company of New Mexico (PNM) service area. The developer is listed as PNM.
The project is currently in the Public Service Company of New Mexico interconnection queue, with an entry date of January 3, 2023. Its proposed commercial operation date is November 1, 2025. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Diamond Tail _x0013_ Clines Corners 345 kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Diamond Tail _x0013_ Clines Corners 345 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2023-07