PNM-IA-PNM-2023-10
210 MW generation in Mckinley, NM · In queue since January 2023 · Proposed COD January 2028
210 MW
Capacity
1
Components
Hydrogen
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
The proposed project PNM-IA-PNM-2023-10 is a 210 MW hydrogen generation project located in McKinley County, New Mexico. The project is listed in the Public Service Company of New Mexico (PNM) interconnection queue with an entry date of January 3, 2023, and a proposed commercial operation date of January 1, 2028. The point of interconnection is the Ambrosia 230 kV Substation.
The project's interconnection status is currently in the System Impact Study phase. The developer is listed as PNM. The project has appeared in recent news coverage regarding hydrogen energy projects in the Western United States.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Ambrosia 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.