PNM-IA-PNM-2023-13
100 MW hybrid in Valencia, NM · In queue since January 2023 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PNM-IA-PNM-2023-13 is a proposed 100 MW hybrid solar and battery project located in Valencia County, New Mexico. The project, which appeared in the Public Service Company of New Mexico (PNM) interconnection queue on January 3, 2023, consists of 100 MW of solar capacity. Its proposed commercial operation date is December 1, 2026.
The project's interconnection status is currently in the System Impact Study phase within the PNM queue. The point of interconnection is the Sun Ranch Switching Station.
Generated from interconnection queue and public data sources
State
NM
County
Valencia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Sun Ranch Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.