PNM-IA-PNM-2023-16
199 MW generation in Roosevelt, NM · In queue since September 2023 · Proposed COD February 2028
199 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-01
The proposed project PNM-IA-PNM-2023-16 is a 199 MW solar generation project located in Roosevelt County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area.
The project is currently in the Public Service Company of New Mexico interconnection queue with an entry date of September 27, 2023. Its interconnection status is listed as "System Impact Study" with a proposed commercial operation date of February 1, 2028. The point of interconnection is the Blackwater 345 kV Station.
Generated from interconnection queue and public data sources
State
NM
County
Roosevelt
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Blackwater 345 kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.