PNM-IA-PNM-2023-21
500 MW hybrid in San Juan, NM · In queue since September 2023 · Proposed COD December 2028
500 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed project PNM-IA-PNM-2023-21 is a 500 MW hybrid solar and battery energy storage development in San Juan County, New Mexico. The project, located in the Western region, is being proposed within the Public Service Company of New Mexico (PNM) interconnection queue. The queue entry date is September 29, 2023, with a proposed commercial operation date of December 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is planned for a new substation off the FW and WW 345 kV line. The project consists of 500 MW of solar photovoltaic generation coupled with battery energy storage.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
New substation off the FW and WW 345 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.