PNM-IA-PNM-2023-26
199.9 MW storage in Luna, NM · In queue since September 2023 · Proposed COD March 2026
199.9 MW
Capacity
1
Components
Battery
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
The proposed energy storage project PNM-IA-PNM-2023-26 is a 199.9 MW battery development in Luna County, New Mexico. The project is being proposed within the Public Service Company of New Mexico (PNM) service area.
As of its queue entry date of September 29, 2023, the project is in the System Impact Study phase of the Public Service Company of New Mexico interconnection queue. The proposed commercial operation date is March 1, 2026. The point of interconnection is the Luna 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Luna
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Luna 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN