PNM-IA-PNM-2023-28
84.24 MW generation in Mckinley, NM · In queue since September 2023 · Proposed COD June 2028
84.24 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
PNM-IA-PNM-2023-28 is a proposed solar generation project located in McKinley County, New Mexico, with a total capacity of 84.24 MW. The project consists of 84.24 MW of solar photovoltaic generation. It is listed in the Public Service Company of New Mexico (PNM) interconnection queue with an entry date of September 29, 2023, and a proposed commercial operation date of June 1, 2028. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is a new substation on the Ambrosia to Yah-Ta-Hey 115 kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
New Substation on Ambrosia to Yah-Ta-Hey 115 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2023-28