PNM-IA-PNM-2023-30
250 MW hybrid in Santa Fe, NM · In queue since September 2023 · Proposed COD April 2029
250 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-01
PNM-IA-PNM-2023-30 is a proposed 250 MW hybrid solar and battery energy project located in Santa Fe County, New Mexico. The development project consists of 250 MW of solar capacity. It is listed in the Public Service Company of New Mexico (PNM) interconnection queue with an entry date of September 29, 2023, and a proposed commercial operation date of April 1, 2029.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is a new substation on the Clines Corners-Diamond Tail 345 kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
New Substation on Clines Corners-Diamond Tail 345 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2023-30