PNM-IA-PNM-2023-31
100 MW hybrid in Mckinley, NM · In queue since September 2023 · Proposed COD December 2028
100 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed project PNM-IA-PNM-2023-31 is a 100 MW solar and battery hybrid development located in McKinley County, New Mexico. The project, which consists of 100 MW of solar generation, is in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of September 29, 2023.
The project's proposed commercial operation date is December 1, 2028. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Ambrosia 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
_x0013_Ambrosia 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.