PNM-IA-PNM-2024-03
225 MW hybrid in Otero, NM · In queue since June 2024 · Proposed COD November 2027
225 MW
Capacity
2
Components
Solar + Battery
1y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-01
The proposed project PNM-IA-PNM-2024-03 is a 225 MW hybrid Solar+Battery project located in Otero County, New Mexico. The project consists of a 150 MW solar component and a 75 MW battery energy storage system. It is interconnected to the Public Service Company of New Mexico (PNM) via the Alamogordo 115 kV Substation.
The project is currently in the System Impact Study phase of the PNM interconnection queue, having entered the queue on June 26, 2024. The proposed commercial operation date is November 1, 2027.
Generated from interconnection queue and public data sources
State
NM
County
Otero
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Alamogordo 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.