PNM-IA-PNM-2024-04
230 MW generation in Santa Fe, NM · In queue since June 2024 · Proposed COD July 2028
230 MW
Capacity
1
Components
Solar
1y 11m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The proposed project PNM-IA-PNM-2024-04 is a 230 MW solar generation project located in Santa Fe County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area. It interconnected into the PNM queue on June 25, 2024, and has a proposed commercial operation date of July 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Norton - Diamond Tail 345 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Norton - Diamond Tail 345 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2024-04