11 MW generation in Luna, NM · In queue since June 2017 · Proposed COD June 2019
11 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2 years
Schedule
84 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-06-01
The proposed project PNM-SGI-PNM-2017-08 is an 11 MW solar generation project located in Luna County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area. It entered the PNM interconnection queue on June 23, 2017, with a proposed commercial operation date of June 1, 2019.
The interconnection agreement for the project has been executed. The point of interconnection is at the Project 1 Gold Feeder 13. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NM
County
Luna
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Project 1 Gold Feeder 13
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.