PNM-SGI-PNM-2017-09
8.25 MW generation in Luna, NM · In queue since June 2017 · Proposed COD June 2019
8.25 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2 years
Schedule
84 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-06-01
The proposed project PNM-SGI-PNM-2017-09 is an 8.25 MW solar generation project located in Luna County, New Mexico. The developer is PNM, also known as Public Service Company of New Mexico.
The project is in the Public Service Company of New Mexico interconnection queue, with a queue entry date of June 23, 2017. The proposed commercial operation date is June 1, 2019, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
NM
County
Luna
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Project 2 West Feeder 11
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-SGI-PNM-2017-09