PRPA-21-08242
350 MW generation in Laramie, WY · In queue since August 2021 · Proposed COD December 2025
350 MW
Capacity
1
Components
Wind
4y 9m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
4y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PRPA-21-08242 is a proposed wind generation project with a total capacity of 350 MW located in Laramie County, Wyoming. The project is being developed by Platte River Power Authority (PRPA) and interconnected to the Rawhide-Roundhouse 230kV point of interconnection. It is currently in the System Impact Study phase of the interconnection process within the PRPA queue, having entered the queue on August 24, 2021. The proposed commercial operation date is December 31, 2025.
The development project consists of 350 MW of wind generation capacity. It is listed as an active project in the interconnection queue. The project has appeared in recent news coverage regarding PRPA's renewable energy development plans.
Generated from interconnection queue and public data sources
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Service Type
—
Point of Interconnection
Rawhide-Roundhouse 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PRPA-21-08242