PRPA-22-07251
250 MW hybrid in Larimer, CO · In queue since July 2022 · Proposed COD March 2028
250 MW
Capacity
1
Components
Gas
3y 10m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
PRPA-22-07251 is a proposed 250 MW hybrid development project consisting of gas and oil technologies located in Larimer County, Colorado. The project is sponsored by Platte River Power Authority (PRPA). It is listed as active in the West region interconnection queue, with a queue entry date of July 25, 2022, and a proposed commercial operation date of March 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is Rawhide 230kV. Recent news coverage has discussed this project.
Generated from interconnection queue and public data sources
State
CO
County
Larimer
Grid Region
Mountain West
Market
—
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Service Type
—
Point of Interconnection
Rawhide 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.