PRPA-22-07252
200 MW hybrid in Larimer, CO · In queue since July 2022 · Proposed COD March 2026
200 MW
Capacity
1
Components
Wind
3y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
PRPA-22-07252 is a proposed 200 MW hybrid wind and battery project located in Larimer County, Colorado. The development project, consisting of 200 MW of wind generation, is in the Platte River Power Authority (PRPA) interconnection queue, under the queue ID PRPA-22-07252.
The project entered the queue on July 25, 2022, with a proposed commercial operation date of March 1, 2026. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Rawhide-Roundhouse 230kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Larimer
Grid Region
Mountain West
Market
—
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Service Type
—
Point of Interconnection
Rawhide-Roundhouse 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PRPA-22-07252