PRPA-24-03011
130 MW storage in Larimer, CO · In queue since March 2024 · Proposed COD January 2027
130 MW
Capacity
1
Components
Battery
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-01
PRPA-24-03011 is a proposed 130 MW battery storage project located in Larimer County, Colorado. The project is being developed by Platte River Power Authority (PRPA) and consists of 130 MW of battery capacity.
The project is currently active in the PRPA interconnection queue as of March 1, 2024, with a proposed commercial operation date of January 1, 2027. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Crossroads 115kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Larimer
Grid Region
Mountain West
Market
—
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Service Type
—
Point of Interconnection
Crossroads 115kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PRPA-24-03011