PSCo-1RSC-2020-02
75 MW storage in Pueblo, CO · In queue since January 2020 · Proposed COD December 2022
75 MW
Capacity
1
Components
Battery
6y 4m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
2y 11m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2022-12-01
The proposed PSCo-1RSC-2020-02 project is a 75 MW battery storage development in Pueblo County, Colorado. The project is interconnected to the Public Service Company of Colorado (PSCo) via the Comanche-Daniels Park 345 kV point of interconnection.
The project is listed in the PSCo interconnection queue with an entry date of January 24, 2020. The proposed commercial operation date is December 1, 2022, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Comanche-Daniels Park 345 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-1RSC-2020-02