PSCo-2RSC-2020-05
250 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD September 2022
250 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
2 years
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-09-30
PSCo-2RSC-2020-05 is a proposed 250 MW hybrid solar and battery project located in Pueblo County, Colorado. The development project, consisting of 250 MW of solar capacity, is in the Public Service Company Of Colorado (PSCo) interconnection queue, with an interconnection queue entry date of September 10, 2020. The proposed commercial operation date is September 30, 2022. The interconnection agreement has been executed.
The point of interconnection (POI) for the project is the Mirasol Switchyard on the Comanche-Midway 230 kV Transmission Line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Mirasol Switchyard on the Comanche- Midway 230 kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.