PSCo-3RSC-2023-02
100 MW storage in Pueblo, CO · In queue since May 2023 · Proposed COD December 2025
100 MW
Capacity
1
Components
Battery
3 years
In Queue
—
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed PSCo-3RSC-2023-02 project is a 100 MW battery storage development in Pueblo County, Colorado. The project consists of a single 100 MW battery component. It is located in the West region and is being proposed by Public Service Company Of Colorado (PSCo).
The project is currently active in the Public Service Company Of Colorado interconnection queue, with an entry date of May 19, 2023. The proposed commercial operation date is December 31, 2025. The point of interconnection is the Mirasol 230 kV Switching Station.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Mirasol 230 kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.