PSCo-GI-2016-4
300 MW generation in Lincoln, CO · In queue since February 2016
300 MW
Capacity
1
Components
Wind
10y 3m
In Queue
IA Executed
IA Status
Total Duration
10y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Commercial operation date not yet determined
The proposed PSCo-GI-2016-4 project is a 300 MW wind generation facility located in Lincoln County, Colorado. The project is being developed within the Public Service Company of Colorado (PSCo) service area. It consists of 300 MW of wind generation capacity.
The project is currently active in the Public Service Company of Colorado interconnection queue, with an original queue entry date of February 24, 2016. The interconnection agreement (IA) for the project has been executed. The point of interconnection (POI) is the Missile Site Substation.
Generated from interconnection queue and public data sources
State
CO
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Missile Site Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2016-4