PSCo-GI-2020-03
199 MW generation in Pueblo, CO · In queue since March 2020 · Proposed COD December 2023
199 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PSCo-GI-2020-03 is a proposed solar generation project with a total capacity of 199 MW, located in Pueblo County, Colorado. The project is in the Public Service Company of Colorado (PSCo) interconnection queue, with an original queue entry date of March 9, 2020. The proposed commercial operation date was December 1, 2023.
The interconnection agreement (IA) for PSCo-GI-2020-03 is currently listed as suspended. The point of interconnection (POI) is the Boone-Comanche 230 kV line.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Boone-Comanche 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2020-03