PSCo-GI-2020-13
374 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD December 2024
374 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PSCo-GI-2020-13 is a proposed 374 MW hybrid solar and battery energy storage project located in Pueblo County, Colorado. The project consists of 374 MW of solar generation. It is interconnected to the Public Service Company of Colorado (PSCo) via the Boone-Midway 230 kV line.
The project entered the PSCo interconnection queue on September 22, 2020, with a proposed commercial operation date of December 1, 2024. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Boone-Midway 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.