PSCo-GI-2021-2
49 MW generation in Weld, CO · In queue since March 2021 · Proposed COD April 2022
49 MW
Capacity
1
Components
Gas
5y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
1y 1m
Schedule
50 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2022-04-01
PSCo-GI-2021-2 is a proposed 49 MW gas-fired generation project located in Weld County, Colorado. The project is interconnected with Public Service Company of Colorado (PSCo) and entered the PSCo interconnection queue on March 22, 2021. The proposed commercial operation date is April 1, 2022, and the interconnection agreement has been executed. The point of interconnection is Fort St Vrain Unit #2.
The development project consists of 49 MW of gas-fired generation capacity. It is listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Weld
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Fort St Vrain Unit #2
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2021-2