PSCo-GI-2021-4
42 MW hybrid in Conejos, CO · In queue since March 2021 · Proposed COD May 2024
42 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-15
The proposed PSCo-GI-2021-4 project is a 42 MW hybrid solar and battery energy storage development in Conejos County, Colorado. The project, located in the Western region, consists of 42 MW of solar generation. It is interconnected to the Public Service Company of Colorado (PSCo) via the Romeo Substation at 69 kV.
The project is in the Public Service Company Of Colorado interconnection queue, with an entry date of March 29, 2021, and a proposed commercial operation date of May 15, 2024. Its interconnection agreement status is currently listed as suspended. The overall project status is also suspended.
Generated from interconnection queue and public data sources
State
CO
County
Conejos
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Romeo Substation 69 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN