Project PSCo-GI-2024-01 — Project Summary

Queue ID
PSCo-GI-2024-01
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Weld, CO
Region
West
Developer
IA Status

PSCo-GI-2024-01

PSCo-GI-2024-01BetaActiveSolarBatteryPSCoLBNL

199 MW hybrid in Weld, CO · In queue since April 2024 · Proposed COD May 2027

199 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2027

Interconnection

Total Duration

3y 1m

Pre-Study0%
Queue EntryApr 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-30

About

PSCo-GI-2024-01 is a proposed 199 MW hybrid solar and battery project located in Weld County, Colorado. The development project consists of 199 MW of solar capacity. It is listed as active in the Public Service Company of Colorado (PSCo) interconnection queue, with an entry date of April 5, 2024. The proposed commercial operation date is May 30, 2027.

The project is located in the western region and interconnects at the Canal Crossing - Ft St Vrain 345 kV line.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Weld

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

Point of Interconnection

Canal Crossing - Ft St Vrain 345 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.