Project PSCo-GI-2024-03 — Project Summary

Queue ID
PSCo-GI-2024-03
Capacity
150 MW
Technology
Solar
Status
active
Location
Adams, CO
Region
West
Developer
IA Status

PSCo-GI-2024-03

PSCo-GI-2024-03BetaActiveSolarPSCoLBNL

150 MW generation in Adams, CO · In queue since April 2024 · Proposed COD March 2029

150 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2029

Interconnection

Total Duration

4y 11m

Pre-Study0%
Queue EntryApr 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-25

About

PSCo-GI-2024-03 is a proposed solar generation project located in Adams County, Colorado, with a total capacity of 150 MW. The project is listed in the Public Service Company of Colorado (PSCo) interconnection queue, with an entry date of April 30, 2024. The proposed commercial operation date is March 25, 2029.

The project consists of 150 MW of solar photovoltaic generation. It is interconnected to the Pawnee-Missile Site 230 kV line. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Adams

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

Point of Interconnection

Pawnee-Missile Site 230 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.