PSCo-GI-2024-06
500 MW hybrid in Morgan, CO · In queue since May 2024 · Proposed COD June 2027
500 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The proposed PSCo-GI-2024-06 project is a 500 MW hybrid solar and battery energy storage development in Morgan County, Colorado. The project consists of 500 MW of solar generation. It is located in the West region and is being proposed to Public Service Company Of Colorado (PSCo).
The project is currently active in the PSCo interconnection queue, with an initial queue entry date of May 8, 2024. The proposed commercial operation date is June 1, 2027, and the point of interconnection is the Story-Pawnee 230 kV line.
Generated from interconnection queue and public data sources
State
CO
County
Morgan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Story-Pawnee 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.