PSCo-GI-2024-08
10 MW storage in Pueblo, CO · In queue since May 2024 · Proposed COD March 2026
10 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2026
Total Duration
1y 10m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
PSCo-GI-2024-08 is a proposed 10 MW battery storage project located in Pueblo County, Colorado. The project is interconnected with Public Service Company of Colorado (PSCo) via the Comanche 345 kV Substation. It entered the PSCo interconnection queue on May 14, 2024, with a proposed commercial operation date of March 31, 2026.
The development project consists of a 10 MW battery energy storage system. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Comanche 345 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2024-08