PSCo-GI-2024-09
199 MW storage in Adams, CO · In queue since May 2024 · Proposed COD December 2027
199 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
PSCo-GI-2024-09 is a proposed 199 MW battery storage project located in Adams County, Colorado. The project, under development by Public Service Company of Colorado (PSCo), entered the Public Service Company Of Colorado interconnection queue on May 15, 2024. The proposed commercial operation date is December 15, 2027, and the point of interconnection is the Riverdale 230 kV Substation.
The project consists solely of battery storage, with a total capacity of 199 MW. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Riverdale 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2024-09