PSCo-GI-2024-11
170 MW hybrid in Saguache, CO · In queue since May 2024 · Proposed COD May 2028
170 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-05
PSCo-GI-2024-11 is a proposed 170 MW hybrid solar and battery energy project located in Saguache County, Colorado. The project consists of 170 MW of solar generation. It is listed in the Public Service Company of Colorado (PSCo) interconnection queue with an entry date of May 17, 2024.
The proposed commercial operation date for the project is May 5, 2028. The point of interconnection is the Poncha-San Luis Valley 230 kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Saguache
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Poncha-San Luis Valley 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSCo-GI-2024-11