Project PSCo-GI-2024-11 — Project Summary

Queue ID
PSCo-GI-2024-11
Capacity
170 MW
Technology
Solar+Battery
Status
active
Location
Saguache, CO
Region
West
Developer
IA Status

PSCo-GI-2024-11

PSCo-GI-2024-11BetaActiveSolarBatteryPSCoLBNL

170 MW hybrid in Saguache, CO · In queue since May 2024 · Proposed COD May 2028

170 MW

Capacity

1

Components

Solar

2 years

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4 years

Pre-Study0%
Queue EntryMay 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-05

About

PSCo-GI-2024-11 is a proposed 170 MW hybrid solar and battery energy project located in Saguache County, Colorado. The project consists of 170 MW of solar generation. It is listed in the Public Service Company of Colorado (PSCo) interconnection queue with an entry date of May 17, 2024.

The proposed commercial operation date for the project is May 5, 2028. The point of interconnection is the Poncha-San Luis Valley 230 kV line. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Saguache

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

Point of Interconnection

Poncha-San Luis Valley 230 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.