Project PSCo-GI-2024-12 — Project Summary

Queue ID
PSCo-GI-2024-12
Capacity
423 MW
Technology
Wind
Status
active
Location
Adams, CO
Region
West
Developer
IA Status

PSCo-GI-2024-12

PSCo-GI-2024-12BetaActiveWindPSCoLBNL

423 MW generation in Adams, CO · In queue since May 2024 · Proposed COD December 2028

423 MW

Capacity

1

Components

Wind

2 years

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 7m

Pre-Study0%
Queue EntryMay 14, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

About

PSCo-GI-2024-12 is a proposed wind generation project with a total capacity of 423 MW. The project is located in Adams County, Colorado, and is being developed within the Public Service Company of Colorado (PSCo) service area. It is interconnected to the Pawnee 345 kV Substation.

The project is currently active in the PSCo interconnection queue, with an entry date of May 14, 2024. The proposed commercial operation date is December 1, 2028.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Adams

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

Point of Interconnection

Pawnee 345 kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.