Project PSCo-GI-2024-14 — Project Summary

Queue ID
PSCo-GI-2024-14
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status

PSCo-GI-2024-14

PSCo-GI-2024-14BetaActiveSolarBatteryPSCoLBNL

150 MW hybrid in Pueblo, CO · In queue since May 2024 · Proposed COD December 2027

150 MW

Capacity

1

Components

Solar

2 years

In Queue

IA Status

COD target: 2027

Interconnection

Total Duration

3y 7m

Pre-Study0%
Queue EntryMay 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

The proposed PSCo-GI-2024-14 project is a 150 MW hybrid solar and battery energy storage development in Pueblo County, Colorado. The project consists of 150 MW of solar photovoltaic generation. It is located in the West region and is being proposed to Public Service Company Of Colorado (PSCo).

The project is currently active in the PSCo interconnection queue, with an entry date of May 17, 2024. The proposed commercial operation date is December 31, 2027. The point of interconnection is the Boone-Midway 230 kV line.

Generated from interconnection queue and public data sources

Project Details

State

CO

County

Pueblo

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

Point of Interconnection

Boone-Midway 230 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.