PSCo-GI-2024-18
150 MW generation in Morgan, CO · In queue since May 2024 · Proposed COD May 2027
150 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
The proposed PSCo-GI-2024-18 project is a 150 MW solar generation project located in Morgan County, Colorado. Interconnecting to the Public Service Company of Colorado (PSCo) via the Pawnee 345 kV Substation, the project entered the PSCo interconnection queue on May 23, 2024. The proposed commercial operation date is May 1, 2027.
The project consists of 150 MW of solar photovoltaic generation capacity. As of the current data, the project is listed as active in the interconnection queue and no Interconnection Agreement (IA) status is available. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
CO
County
Morgan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
—
Point of Interconnection
Pawnee 345 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.