PSE-1 Pre Jan 2004
200 MW generation in Kittitas, WA · In queue since February 2003 · Proposed COD November 2004
200 MW
Capacity
1
Components
Wind
23y 3m
In Queue
IA Pending
IA Status
COD target: 2004
Total Duration
1y 9m
Schedule
261 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2004-11-14
The proposed project, identified as PSE-1 Pre Jan 2004, is a 200 MW wind generation facility located in Kittitas County, Washington. The project is being developed by Puget Sound Energy (PSE). It consists of 200 MW of wind capacity.
The project is in the Puget Sound Energy interconnection queue with an entry date of February 5, 2003. The proposed commercial operation date is November 14, 2004, and the interconnection agreement is currently pending. The point of interconnection is the IP Line.
Generated from interconnection queue and public data sources
State
WA
County
Kittitas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Service Type
—
Point of Interconnection
IP Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSE-1 Pre Jan 2004