218.78 MW generation in Lewis, WA · In queue since July 2021 · Proposed COD October 2025
218.78 MW
Capacity
1
Components
Gas
4y 10m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-15
PSE-113 is a proposed 218.78 MW gas-fired generation project located in Lewis County, Washington. The project, under development by Puget Sound Energy (PSE), entered the Puget Sound Energy interconnection queue on July 27, 2021, with a proposed commercial operation date of October 15, 2025.
The interconnection agreement for PSE-113 is currently listed as suspended. The point of interconnection is planned at a proposed new 115 kV substation between the existing Tono, Blumaer, and Rochester substations.
Generated from interconnection queue and public data sources
State
WA
County
Lewis
Grid Region
Mountain West
Market
—
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Service Type
—
Point of Interconnection
Primary: Proposed new 115 kV substation between Tono, Blumaer, and Rochester substations
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.