Project PSE-139 — Project Summary

Queue ID
PSE-139
Capacity
130 MW
Technology
Battery
Status
active
Location
King, WA
Region
West
Developer
IA Status
Cluster Study

PSE-139

PSE-139BetaActiveBatteryPSELBNL

130 MW storage in King, WA · In queue since December 2023 · Proposed COD December 2028

130 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection

Total Duration

5 years

Impact Study25%
Queue EntryDec 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-30

About

PSE-139 is a proposed 130 MW battery storage project located in King County, Washington. The project is being developed by Puget Sound Energy (PSE) and consists entirely of battery technology. It is currently active in the Puget Sound Energy interconnection queue (PSE-139) with an entry date of December 15, 2023.

The proposed commercial operation date for PSE-139 is December 30, 2028. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Mount Si 115 kV Substation. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

King

Grid Region

Mountain West

Market

Developer

Utility

Puget Sound Energy

Entity

PSE

Service Type

Point of Interconnection

Mount Si 115 kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.