Project PSE-145 — Project Summary

Queue ID
PSE-145
Capacity
100 MW
Technology
Battery
Status
active
Location
Whatcom, WA
Region
West
Developer
IA Status
Cluster Study

PSE-145

PSE-145BetaActiveBatteryPSELBNL

100 MW storage in Whatcom, WA · In queue since April 2024 · Proposed COD May 2027

100 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 1m

Impact Study25%
Queue EntryApr 12, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

About

PSE-145 is a proposed 100 MW battery storage project located in Whatcom County, Washington. The project is being developed by Puget Sound Energy (PSE) and is currently listed as active in the PSE interconnection queue, with an entry date of April 12, 2024. The proposed commercial operation date is May 31, 2027.

The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Custer Substation, located at coordinates 48.90451433, -122.6251608.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Whatcom

Grid Region

Mountain West

Market

Developer

Utility

Puget Sound Energy

Entity

PSE

Service Type

Point of Interconnection

Custer Substation (48.90451433, -122.6251608)

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.